高广运, 吴德顺, 毕俊伟. 2018: 新建输水隧道对既有宣杭铁路路基变形影响研究. 工程地质学报, 26(s1): 227-233. DOI: 10.13544/j.cnki.jeg.2018151
    引用本文: 高广运, 吴德顺, 毕俊伟. 2018: 新建输水隧道对既有宣杭铁路路基变形影响研究. 工程地质学报, 26(s1): 227-233. DOI: 10.13544/j.cnki.jeg.2018151
    GAO Guangyun, WU Deshun, BI Junwei. 2018: INVESTIGATON DEFORMATION IMPACT OF A WATER SUPPLY TUNNEL EXCAVATION ON XUANHANG EXISTING RAILWAY SUBGRADE. JOURNAL OF ENGINEERING GEOLOGY, 26(s1): 227-233. DOI: 10.13544/j.cnki.jeg.2018151
    Citation: GAO Guangyun, WU Deshun, BI Junwei. 2018: INVESTIGATON DEFORMATION IMPACT OF A WATER SUPPLY TUNNEL EXCAVATION ON XUANHANG EXISTING RAILWAY SUBGRADE. JOURNAL OF ENGINEERING GEOLOGY, 26(s1): 227-233. DOI: 10.13544/j.cnki.jeg.2018151

    新建输水隧道对既有宣杭铁路路基变形影响研究

    INVESTIGATON DEFORMATION IMPACT OF A WATER SUPPLY TUNNEL EXCAVATION ON XUANHANG EXISTING RAILWAY SUBGRADE

    • 摘要: 为研究新建输水隧道对既有铁路路基安全性的影响,以杭州大毛坞-仁和大道输水隧道盾构下穿宣杭铁路为工程背景,运用Midas NX有限元分析软件,建立三维数值分析模型模拟盾构施工过程,研究了输水隧道盾构施工对既有铁路路基变形的影响,并验证了分块加固方案(劈裂注浆加固区、旋喷桩加固区以及压密注浆加固区)的有效性。研究发现:采取分块加固措施后,输水隧道盾构施工对上部既有铁路路基在水平方向(X,Y方向)上的位移影响较小;加固区范围内,盾构下穿引起的变形以竖向沉降为主,最大沉降为8.6 mm,加固区外以竖向隆起为主,最大隆起为17.0mm;随着盾构施工不断推进,变形最大值的位置随之迁移。研究表明分块加固措施可以较好的控制由输水隧道盾构施工引起的上部既有铁路路基变形,以确保既有铁路的运营安全。

       

      Abstract: To study the safety influence of a newly built water supply tunnel on the existing railway subgrade, a three dimensional numerical model was established by Midas NX to simulate the shield construction, based on the Damaowu-Renhe water supply tunnel shield underneath the Xuan-Hang railway located in Hangzhou. The displacement of the existing railway subgrade was calculated and the effectivity of the sub-regional reinforcement(splitting grouting reinforcement area, high pressure jet grouting pile reinforcement area and compaction grouting reinforcement area) was studied. Results show that due to the reinforcement measures, the lateral displacement induced by the tunnel shield construction is small enough to be neglected. In the reinforced area, the deformation is mainly vertical settlement with the maximum value of 8.6mm; and the uplift is the main deformation outside the reinforced area which the maximum value is 17.0mm. The maximum displacement location changes with the shield excavation. The sub-regional reinforcement measures can reduce the existing railway subgrade deformation induced by the tunnel shield construction effectively, which insures the safety operation of the existing railway.

       

    /

    返回文章
    返回