周洪福, 韦玉婷, 聂德新. 2009: 黄河上游戈龙布滑坡高速下滑成因机制及堵江分析. 工程地质学报, 17(4): 483-488.
    引用本文: 周洪福, 韦玉婷, 聂德新. 2009: 黄河上游戈龙布滑坡高速下滑成因机制及堵江分析. 工程地质学报, 17(4): 483-488.
    ZHOU Hongfu, WEI Yuting, NIE Dexin. 2009: FORMATION MECHANISM OF HIGH-SPEED GELONGBU LANDSLIDE AND ASSOCIATED BLOCKAGE OF UPPER REACH YELLOW RIVER. JOURNAL OF ENGINEERING GEOLOGY, 17(4): 483-488.
    Citation: ZHOU Hongfu, WEI Yuting, NIE Dexin. 2009: FORMATION MECHANISM OF HIGH-SPEED GELONGBU LANDSLIDE AND ASSOCIATED BLOCKAGE OF UPPER REACH YELLOW RIVER. JOURNAL OF ENGINEERING GEOLOGY, 17(4): 483-488.

    黄河上游戈龙布滑坡高速下滑成因机制及堵江分析

    FORMATION MECHANISM OF HIGH-SPEED GELONGBU LANDSLIDE AND ASSOCIATED BLOCKAGE OF UPPER REACH YELLOW RIVER

    • 摘要: 黄河上游戈龙布滑坡位于积石峡水电站库区内,经过现场调查可知,戈龙布滑坡为一大型滑坡,整个滑坡体积达到5040万m3,一共分为4个区。研究表明,戈龙布滑坡成因机制为滑移-拉裂型,滑坡在黄河右岸经过高速远程下滑过后撞击上游山体,部分滑体越过黄河堆积于左岸并堵塞黄河达数百年,堰塞湖内有厚度达30余米的纹泥沉积,初步分析滑坡坝的高度在100m左右,库水深在70m左右,滑坡堵江时代在Q4时期。滑坡坝溃决后导致黄河改道,残留的滑体分别位移黄河的左岸和右岸。

       

      Abstract: The Gelongbu landslide located at the reservoir region of Jishixia hydropower station dam in upper reach Yellow River. Its volume was of 50.4106 m3. It had 4 regions. The result of landslide investigation indicates that the formation mechanism of Gelongbu landslide is sliding-fracturing. The landslide debris flew down with a high speed on the right side of Yellow River and hit a hill. . Part of its debris flew across the river and deposited on the left side. Its debris had blocked the river for several hundred years and formed a landslide dam like. The thickness of sediment in the landslide dam lake was 30 m based on the measurement of this investigation. Height of the landslide dam was about 100 m and water depth of the lake was about 70 m based on the preliminary analysis of this investigation. The epoch of landslide is Q4. The debris were still left on left and right sides of Yellow River. The Yellow river path was changed at this location. It was possibly due to a sudden collapse of the landslide dam. 

       

    /

    返回文章