李会中, 郝文忠, 潘玉珍, 肖云华, 郭飞. 2015: 金沙江乌东德水电站坝址区河床深厚覆盖层工程特性研究. 工程地质学报, 23(s1): 509-515. DOI: 10.13544/j.cnki.jeg.2015.s1.078
    引用本文: 李会中, 郝文忠, 潘玉珍, 肖云华, 郭飞. 2015: 金沙江乌东德水电站坝址区河床深厚覆盖层工程特性研究. 工程地质学报, 23(s1): 509-515. DOI: 10.13544/j.cnki.jeg.2015.s1.078
    LI Huizhong, HAO Wenzhong, PAN Yuzhen, XIAO Yunhua, GUO Fei. 2015: STUDY ON THE ENGINEERING PROPERTIES OF THE DEEP OVERBURDEN LAYER AT DAM SITE OF WUDONGDE HYDROPOWER STATION ON JINSHA RIVER. JOURNAL OF ENGINEERING GEOLOGY, 23(s1): 509-515. DOI: 10.13544/j.cnki.jeg.2015.s1.078
    Citation: LI Huizhong, HAO Wenzhong, PAN Yuzhen, XIAO Yunhua, GUO Fei. 2015: STUDY ON THE ENGINEERING PROPERTIES OF THE DEEP OVERBURDEN LAYER AT DAM SITE OF WUDONGDE HYDROPOWER STATION ON JINSHA RIVER. JOURNAL OF ENGINEERING GEOLOGY, 23(s1): 509-515. DOI: 10.13544/j.cnki.jeg.2015.s1.078

    金沙江乌东德水电站坝址区河床深厚覆盖层工程特性研究

    STUDY ON THE ENGINEERING PROPERTIES OF THE DEEP OVERBURDEN LAYER AT DAM SITE OF WUDONGDE HYDROPOWER STATION ON JINSHA RIVER

    • 摘要: 深厚覆盖层工程特性研究是长期困扰岩土工程勘察领域的难点之一。金沙江乌东德水电站坝址区河床覆盖层深厚、成因复杂、物质组成与结构不均, 其物理、水理、力学等工程特性研究难度大, 高围堰与深基坑稳定问题突出。为了研究确定河床覆盖层工程特性、提出工程设计所需物理力学参数, 勘察过程中将动力触探、旁压试验、抽水试验、声波测试、钻孔彩电等原位测试与室内土常规试验、模拟级配样试验等室内试验相结合, 进行了专题研究并取得了丰硕成果, 成功破解了深厚覆盖层工程特性研究难题, 为乌东德水电站高围堰与深基坑工程设计提供了可靠依据, 可供类似工程借鉴参考。

       

      Abstract: The research on the engineering properties of the deep overburden layer is one of the long-term problems in the field of geotechnical engineering investigation. The overburden layer in the dam area of Wudongde Hydropower Station on Jinsha River is deep, and it has complex causes and uneven material composition and structure, which make it difficult to study on the mechanical characteristics, physical and water-physical properties. High cofferdam and deep foundation pit stability problems are serious. In order to determine the engineering properties of the overburden layer and propose the physical and mechanical parameters required for engineering design, some field tests and laboratory tests have been done, such as dynamic penetration test, lateral pressure test, pumping test, sonic wave test, borehole digital TV, routine soil test and simulated gradation sample The engineering problems of the deep overburden layer were solved by conducting comparison and discussion, a reliable basis for the engineering design of high cofferdam and deep foundation pit of Wudongde Hydropower Station was provided. Those methods can be used for similar engineering projects.

       

    /