阴晓冬, 张常亮, 李同录, 张国伟. 2016: 采空区对输电线路稳定性影响三维数值模拟分析. 工程地质学报, 24(s1): 1326-1335. DOI: 10.13544/j.cnki.jeg.2016.s1.195
    引用本文: 阴晓冬, 张常亮, 李同录, 张国伟. 2016: 采空区对输电线路稳定性影响三维数值模拟分析. 工程地质学报, 24(s1): 1326-1335. DOI: 10.13544/j.cnki.jeg.2016.s1.195
    YIN Xiaodong, ZHANG Changliang, LI Tonglu, ZHANG Guowei. 2016: THE STUDY OF GOAF INFLUENCE ON THE STABILITY OF TRANSMISSION LINE BASED ON THREE-DIMENSIONAL NUMERICAL SIMULATION ANALYSIS. JOURNAL OF ENGINEERING GEOLOGY, 24(s1): 1326-1335. DOI: 10.13544/j.cnki.jeg.2016.s1.195
    Citation: YIN Xiaodong, ZHANG Changliang, LI Tonglu, ZHANG Guowei. 2016: THE STUDY OF GOAF INFLUENCE ON THE STABILITY OF TRANSMISSION LINE BASED ON THREE-DIMENSIONAL NUMERICAL SIMULATION ANALYSIS. JOURNAL OF ENGINEERING GEOLOGY, 24(s1): 1326-1335. DOI: 10.13544/j.cnki.jeg.2016.s1.195

    采空区对输电线路稳定性影响三维数值模拟分析

    THE STUDY OF GOAF INFLUENCE ON THE STABILITY OF TRANSMISSION LINE BASED ON THREE-DIMENSIONAL NUMERICAL SIMULATION ANALYSIS

    • 摘要: 为研究地下煤矿采空区垮塌对其地表变形及其上建筑物安全性的影响,本文依托750kV渭延线送电工程,以Z149#~Z154#段输电线路为研究对象,利用MIDAS数值模拟软件建立了其三维分析模型,通过两种工况的模拟,对场区在不同开采作用形成的采空区影响下塔基变形及邻近边坡的稳定性进行了分析,获得如下结论:(1)现有工况条件下,形成的采空区主要对149#塔及150#塔产生较大影响,模拟结果显示,149#塔与150#塔之间Z方向位移最大达到0.7259m,与实际观测得到的该段地表最大沉降0.65m相比基本一致,模拟结果能反映实际变形情况;开采对149#、150#、151#塔塔基的不均匀沉降有所影响,塔脚间最大沉降差达到0.0091m,与现场实测150#塔脚最大沉降差0.0085m相比,结果基本一致;最不利剖面仅出现在149#塔、150#塔附近的边坡中,但均未形成贯通性滑移面,不会出现边坡失稳。(2)最终工况条件下,形成的采空区对场区内所有塔基均有影响,各塔Z方向的位移与现有工况相比均呈增大趋势;开采造成的塔脚最大沉降最大可达0.0120m,且150#塔、151#塔、152#塔产生的最大沉降差过大,需加强监测;各塔附近的边坡均受到开采的影响,但未形成贯通性滑移面,不会出现边坡失稳。本文研究内容可为采空区上覆输电线路及其他相关建筑物的安全运营和防治提供技术支持和参考。

       

      Abstract: In order to study the relationships between goaf collapse caused by underground coal-mining and the safety of buildingsandsurface deformation, we analyzed the deformation of pylon foundation affecting by different mine goaf due to different mining methods, as well as the stability of adjacentslope in an area. This area is located in the district of Z149#~Z154# transmission line, which is based on the 750kV power transmission project. A MIDAS numerical simulation software is used to establish a three-dimensional analysis model and two working conditions are simulated in this paper, some conclusions are obtained as follows:(1) under the existing working conditions, the goaf mainly affected the tower of 149# and the tower of 150#, and the simulation results show thatbetween the tower of 149# and the tower of 150#,vertical displacement have its peakat 0.7259m, which is in consonance with the actual observation of the maximum surface settlement of 0.65m, showing that the simulation results can approximately reflect the actual deformation results; exploitation can cause 149#, 150# and 151# tower' foundation uneven settlement, the maximum difference in settlement between towel foots reachto 0.0091m, which is in accordance with the measured value of 150# tower with its maximum difference in settlement is 0.0085m, and likewise, the simulation results suit actual results well; and the least favorable profiles only appear in slopes in the vicinity between the 149# tower and 150# tower, but no continuous slip surface is formed, and no slope instability would be formed.(2) Under the final working condition, all the already formedgoaf in this field have impacts on pylon foundations, and compared with the existing working conditions, the vertical displacementsof each towel display an increasing trend; the mining-caused maximum settlement in tower foots could reach as high as 0.0120m, and tower of 150#, 151# and 152# produced an oversized subsidence difference, so strengthened monitoring should be warranted; although slopes near the tower are all influencedby mining activities, there are not continuous slip surface formed, as a result, no slope instability would occur. This paper can provide technical support and reference for the safe operation and control of the transmission line and other related structures which are located in the goaf areas.

       

    /

    返回文章
    返回