凡亚, 胡金山. 2020: 西部高山峡谷区特大电站泄洪洞进水口边坡与塔基优化处理——以长河坝水电站为例. 工程地质学报, 28(S1): 225-229. DOI: 10.13544/j.cnki.jeg.2020-332
    引用本文: 凡亚, 胡金山. 2020: 西部高山峡谷区特大电站泄洪洞进水口边坡与塔基优化处理——以长河坝水电站为例. 工程地质学报, 28(S1): 225-229. DOI: 10.13544/j.cnki.jeg.2020-332
    FAN Ya, HU Jinshan. 2020: OPTIMIZATION TREATMENT OF INTAKE SLOPE AND TOWER FOUNDATION OF TUNNEL SPILLWAY FOR EXTRA-LARGE POWER STATION IN WEST MOUNTAIN CANYON AREA—TAKING CHANGHEBA HYDROPOWER STATION AS AN EXAMPLE. JOURNAL OF ENGINEERING GEOLOGY, 28(S1): 225-229. DOI: 10.13544/j.cnki.jeg.2020-332
    Citation: FAN Ya, HU Jinshan. 2020: OPTIMIZATION TREATMENT OF INTAKE SLOPE AND TOWER FOUNDATION OF TUNNEL SPILLWAY FOR EXTRA-LARGE POWER STATION IN WEST MOUNTAIN CANYON AREA—TAKING CHANGHEBA HYDROPOWER STATION AS AN EXAMPLE. JOURNAL OF ENGINEERING GEOLOGY, 28(S1): 225-229. DOI: 10.13544/j.cnki.jeg.2020-332

    西部高山峡谷区特大电站泄洪洞进水口边坡与塔基优化处理——以长河坝水电站为例

    OPTIMIZATION TREATMENT OF INTAKE SLOPE AND TOWER FOUNDATION OF TUNNEL SPILLWAY FOR EXTRA-LARGE POWER STATION IN WEST MOUNTAIN CANYON AREA—TAKING CHANGHEBA HYDROPOWER STATION AS AN EXAMPLE

    • 摘要: 西部高山峡谷区山高坡陡,在边坡开挖时即使很陡的开挖坡比也会产生的很高的坡高,导致处理难度大,工期长。因此有必要尽量少开挖,及时进行强支护,对泄洪洞进口做到"高清坡、强支护、低开口、早进洞"。这样能大大降低开挖坡坡高,降低施工难度,减少工期及节约投资。泄洪洞进口边坡优化后,塔基基础外移,离坡面近,需注意岩体卸荷及结构面不利组合塔基基础边坡不利影响,进行稳定性分析与计算,必要时进行支护工程处理措施。本文总结了大渡河上特大电站长河坝水电站泄洪洞进水口边坡优化及塔基基础边坡等成功的处理经验,可为其他类似工程提供经验借鉴。

       

      Abstract: The mountain is high and steep in the western mountain canyon area. Even a very steep excavation slope ratio will produce a very high slope during slope excavation, resulting in difficult treatment and long construction period. Therefore, it is necessary to excavate as little as possible, carry out strong support in time, and achieve "high cleaning up, strong support, low opening and early entry" for the entrance of the spillway tunnel. In this way, the slope height of excavation can be greatly reduced, the construction difficulty can be reduced, the construction period can be reduced, and the investment can be saved. After the intake slope of the tunnel spillway was optimized, the tower foundation moved outward and was close to the slope surface. Attention should be paid to the unloading of rock mass and the adverse effects of unfavorable combination of structural planes on the slope below the tower foundation, stability analysis and calculation should be carried out, and support treatments should be taken when necessary. This paper summarized the successful treatment experience of flood discharge tunnel intake slope optimization and tower foundation slope in Changheba hydropower project on Dadu river, which can provide experience for other similar projects.

       

    /

    返回文章
    返回