LI Dongli, YAN E'chuan, LEI Dong. 2007: THE RESEARCH OF CAST-IN-PLACE PILE QUALITY CONTROL OF THE POWER PLANT PROJECT IN QINZHOU AND NUMERICAL SIMULATION OF THE FLAW PILE. JOURNAL OF ENGINEERING GEOLOGY, 15(S1): 666-670.
    Citation: LI Dongli, YAN E'chuan, LEI Dong. 2007: THE RESEARCH OF CAST-IN-PLACE PILE QUALITY CONTROL OF THE POWER PLANT PROJECT IN QINZHOU AND NUMERICAL SIMULATION OF THE FLAW PILE. JOURNAL OF ENGINEERING GEOLOGY, 15(S1): 666-670.

    THE RESEARCH OF CAST-IN-PLACE PILE QUALITY CONTROL OF THE POWER PLANT PROJECT IN QINZHOU AND NUMERICAL SIMULATION OF THE FLAW PILE

    • Based on the geological condition and foundation treatment method of the power plant project in QinZhou,this paper studied the key point of quality control during the treatment project and the possible flaw pile during construction,preventive measures and solutions are suggested.On this basis,the method of numerical simulation was used,a model of flaw pile is stalished,the plastic zone,the stress,the displacement of different parts of flaw pile are calculated,and a possible influence of the flaw is analyzed.Some useful guidance of dealing with the incidents during the construction of cast-in-place pile for engineers are given in the paper and a new thinking for mechanism of flaw pile is provided.
    • loading

    Catalog

      /

      DownLoad:  Full-Size Img  PowerPoint
      Return
      Return